The major performance functions for
a curtain wall system include structural safety,
thermal insulation, sound insulation, and
water-tightness performance. Except the
water-tightness performance, all other performance
functions can generally be predicted and designed
based on rational analyses or laboratory tests.
It is well known in the curtain wall
industry that the water-tightness performance is the
most difficult parameter to evaluate due to the
following experienced facts.
1. Frequently reported by testing
laboratory¡¦s manager that 90 to 95 percent of test
mock-up failed the first water test.
2. It can be logically recognized
that the workmanship on a mock-up is better than
that on the real building.
3. The reported percentage of
incidents of water leakage problem within the first
year of curtain wall enclosure is known to be very
low.
4. Remedial work is allowed to fix
the water leakage until the mock-up passed the test.
5. The water leakage problem on a
real building often occurs in a rain storm condition
with much less intensity than that was used on the
successful mock-up test in both the amount of water
and the pressure differential.
6. Once the water leakage problem
has been detected on a building, it will become a
multiple recurrence problem within a year if no
successful remedial work is executed.
The following logical conclusions
can be drawn from the above six experienced facts.
C1 : The test condition is much more
severe than the water leakage condition experienced
in a real building.
C2 : Passing a test can not be used
as a measure of water-tightness performance of the
real building.
C3 : Passing a water test at a
higher differential air pressure is not an
indication of better water-tightness performance on
the real building.
C4 : The real issue is the aging
effect on the water-tightness performance of the
curtain wall system and the inaccurate simulation of
the nature in the laboratory.
Based on the above logical
conclusions, the state of the art laboratory testing
methods and procedures offer very little clue to
tell a good curtain wall system from a bad one. A
practical and reliable rating system is urgently
needed to promote the progress of technology.
Problems of State-of-the Art
Water-tightness Performance Test Methods
1. Simulation of the Natural Rain.
a. Intensity of Rain Water on the Wall Surface : Typically a fixed amount of
water per unit area of the mock-up wall surface
is sprayed onto the wall surface from a fixed
distance from the wall surface by a grid of
multiple nozzles spaced at a fixed distance
between them. The amount of water, the nozzle
distance from the wall, the nozzle spacing, and
the type of nozzle vary from country to country.
However, they are the unified test set-up within
a country regardless of the size of the building
and the weather variations within the country.
Therefore, the true simulation of the natural
rain for a particular building at a particular
location is highly questionable. In addition,
comparing the observed amount of water running
on the wall surface of a mock-up to that on the
wall surface of a highrise building, one can
easily reach the following two conclusions.
First, in a heavy rain with mild wind condition,
the two conditions are about equal. Second, in a
heavy rain with high wind condition, the amount
of water running on the wall surface of a
highrise building is much less than that on a
test wall. For a single defense system such as a
wet seal system, the test performance is not
sensitive to the amount of water on the test
wall surface. For an advanced modern system such
as a pressure equalized system, excessive water
on the test wall surface might restrict or
disable the pressure equalization mechanism
and/or cause the overflow of the drainage
mechanism. Therefore, the true simulation of the
amount of water running on the wall surface of a
real building must be evaluated as a function of
the positive wind pressure on the test wall.
b. Method of Providing Water on
the Wall Surface of Test Mock-up : Each spraying
nozzle is perpendicular to the wall surface with
a cone-shaped spraying pattern. Even though this
mode of providing water on the wall surface can
not be found in the natural rain, the earlier
generations of curtain wall system are not
sensitive to the water spaying pattern. However,
the more advanced modern curtain wall systems
such as Open Joint Unitized System and Airloop
System are often sensitive to the water spraying
pattern. For example, the spraying water is
stationarily directed upwardly on the upper
portion of the spraying cone, if the placement
of the nozzle fits a particular orientation,
this steady stream of water may be shooting at
the open space designed for air entry with some
tolerance for incidental water entry. The
tolerance for incidental water entry would
surely be exceeded by the steady entry of the
spraying water causing the overflow of the
internal drainage capability. Therefore, a more
realistic method of delivering the water onto
the test wall surface must be developed for
testing the more advanced modern curtain wall
systems.
2. Simulation of the Natural Wind
a. Intensity of Differential Air
Pressure : Without remedial work after the first
occurrence of water leakage problem, most of the
reported water leakage conditions recur in a
relatively mild rain storm situation. From the
above discussions on the need of a rating
system, it can be logically concluded that the
reason for the first occurrence of water leakage
is due to the degradation of the water sealing
property of the system rather than the
water-tightness resistance to the intensity of
the differential air pressure. For example, for
a wet seal system, if the caulking application
is perfect, the system may be able to sustain a
differential air pressure of 3000 Pa in the
water test without leakage. However, the perfect
seal may become imperfect after one year of
service due to sealant stress fatigue caused by
various structural movements and water leakage
will occur at a very mild rainstorm situation.
Therefore, the current concept of resisting
water leakage at a higher differential air
pressure is an absolute measure of
water-tightness performance is highly
questionable.
b. Method of Providing
Differential Air Pressure on the Mock-up : To
this writer¡¦s knowledge, there are four
different methods of creating the differential
air pressure on a mock-up. The first method is
known as static pressure method using a vacuum
chamber and is commonly used in USA. In this
method, a sealed chamber is built on the
interior side of the test wall and a negative
differential air pressure is created in the
chamber by extracting the air from the chamber.
The second method is known as dynamic pressure
method in association with the vacuum chamber
method and is commonly used in USA. In this
method, a positive differential air pressure on
the test wall is created by real wind generated
by a big fan normally powered by an airplane
propellant engine or a car engine. The third
method is known as static pressure method using
a pressure chamber and is commonly used in
countries outside USA. In this method, a sealed
chamber is built in front of the outside wall
surface and a positive differential air pressure
is created inside the chamber by blowing air
into the chamber. The fourth method is known as
dynamic pressure method in association with the
pressure chamber method and is commonly used in
countries outside USA. In this method, the
cyclic positive pressure inside the chamber is
caused to fluctuate between a maximum and a
minimum with a predetermined cycle period by
controlling the air supply into the chamber.
Again, the earlier generations of curtain wall
system are not sensitive to the method of
providing the differential air pressure.
However, the more advanced modern curtain wall
systems, such as Open Joint Unitized System and Airloop System, are more sensitive to the mode of providing
the differential air pressure. For example, water ingress along a seam due to
the capillary action is much easier by a steady
vacuum force (equivalent to pulling an object on
a friction floor) from inside than by a steady
positive force from outside (equivalent to
pushing an object on a friction floor). Since
water leakage problem is always associated with
a positive wind pressure, the positive pressure
chamber method should be considered as the more
accurate simulation of the natural wind
pressure. Another example is the effect on the
pressure equalization mechanism in an open joint
system. The true nature of wind is dynamic and
the pressure is caused by the impact of the air
mass. The impacting air mass must rebound from
the wall surface and go around the building.
There is a time lag between the wind pressure on
the wall surface and the pressure equalization
in the wall cavity. This time lag would prevent
water leakage due to continuous water ingress in
an open joint system. Therefore, the dynamic
pressure method should be considered as the more
accurate simulation of the wind pressure.
Furthermore, in the natural wind condition, the
rebounding air mass would move the water around
on the wall surface and carry away part of the
water on the wall surface. This behavior should
have some impact on the performance of an open
joint system but is not simulated by the fourth
method. Therefore, the second method should be
considered as the most accurate simulation of
the natural wind.
3. Simulation of the Effects of Long
Term Cyclic Structural Movements
a. Effects of Thermal Movements
: The anticipated thermal load on the components
of a curtain wall system at a specific
geographic location and the thermal movement of
each component material can normally be
predicted with high degree of confidence. The
significance of the sealant line thermal stress
induced by the thermal load depends on the
curtain wall system design. For an open joint
design, the sealant line thermal stress is
typically insignificant. For a restrained joint
design, repeated long term thermal cycles could
cause sealant line failure due to stress
fatigue. The state-of-the-art mock-up testing
procedure does not take into account the effect
of thermal movement.
b. Effects of Wind Load in the
Direction Perpendicular to the Wall Surface :
The sealant line stress due to wind load is
caused by the perimeter restraint on the facing
material against the membrane type of
deformation. This type of effect is difficult to
predict by theoretical analysis and is simulated
in most of the mock-up testing procedures in
many countries.
c. Effects of Story Drift due to
Wind Load or Seismic Load : For most curtain
wall systems, the story drift would tend to
change the shape of the facing material due to
the tilting of mullions which are fixed to the
floor slab edge. Most of the facing materials
are relatively rigid against in-plane shear
distortion caused by the story drift and the
curtain wall component to give is the perimeter
sealant line on the facing material. Therefore,
sealant line dislocation and/or sealant line
failures are commonly caused by the story drift
of the building. The effect of story drift is
simulated in most of the mock-up testing
procedures in many countries.
d. Effects of Inter-Floor
Deflection due to Floor Live Load : Since the
curtain wall supporting mullions are secured to
the edge of the floor slab, except the dead
loaded mullion design, an inter-floor deflection
would cause the curtain wall joints to move,
some to increase the joint gap and some to
reduce the joint gap. The most common method of
simulating the effect of inter-floor deflection
is to conduct the water test at the neutral
position after performing three deflection
cycles in dry condition. Since the inter-floor
deflection could occur during a rainstorm,
water-tightness performance test should be
conducted at the maximum inter-floor deflection
condition. This test condition has not been
specified in most test protocol worldwide.
4. Simulation of Aging Effects on
Sealant Material Properties There is no practical
direct method of simulating the aging effect on a
test mockup. The effects of structural movements are
normally considered as the indirect measure of the
aging effect.
5. Simulation of Rainstorm Duration.
The standard water test duration most commonly used
in USA is 15 minutes. In other country such as
China, the standard water test involves a maximum of
five steps of step-wise increasing pressure with 10
minutes duration at each pressure step (i.e. maximum
test duration of 50 minutes).
Recommended Testing Procedures for
Performance Rating System
1. Method of Simulating Wind
Effects
To simulate the wind effects
including the dynamic nature and the air mass
rebounding behavior for accurate water-tightness
performance evaluation for all curtain wall system,
the following alternative wind simulating methods
are recommended.
a. Adopt the second test method
(dynamic) by using a fan powered by an airplane
propellant engine or car engine to create the
wind effect on the exterior wall surface of a
mock-up in association with an interior vacuum
chamber.
b. Modify the fourth test method
(dynamic) by adding some fans inside the
pressure chamber during the water test to create
the air mass rebounding behavior.
2. Simulation and Selection of
Wind and Rain Intensity
There are two considerations for
long term water-tightness performance. The first is
the performance after enduring the maximum design
loads such as 50-year recurrence interval wind force
and seismic load. The second is the performance
after enduring 1-year recurrence interval wind force
and seismic force repeatedly over several years. The
water leakage problem is an annual concern rather
than a concern of once in 50 years. Therefore, the
annual weather condition should be considered for
conducting the water test. The following concept
parameters are recommended.
a. Use the following three grades of test pressure for the rating system.
Gade A : 1500 PaGrade B :
750 Pa
Grade C : 500 Pa
b. Use rows of perforated pipes
to deliver uniformly distributed streams of
water downwardly onto the test wall surface at
an angle of approximately 45 degrees to the
vertical.
c. Use the following amount of
water to be delivered to the test wall surface.
For Grade A test: 2 liters per minutes per
square meter of test wall surface. For Grade B
test: 3 liters per minutes per square meter of
test wall surface. For Grade C test: 4 liters
per minutes per square meter of test wall
surface.
3. Duration for Water Test
Considering the typical duration of
serious combination of rain and wind, it is
recommended to use 30 minutes as the standard
duration for water test.
4. Selection of Test Parameters
for Structural Movements
The first consideration is that the
wall should not leak after experiencing the maximum
structural design displacements due to wind,
seismic, and live loads. Therefore, the maximum
structural design load tests should be conducted
before conducting the first water test. The second
consideration is that the wall should not leak after
experiencing the daily structural movements for a
complete annual cycle. This would require to conduct
the structural tests for many cycles at a much less
load intensity. Due to the fact that the story drift
cycles can be conducted at a relatively rapid speed
and the effect on the degradation of the sealing
integrity are expected to be more severe, it is
recommended to use the cyclic story drift tests
exclusively for this simulation due to time and cost
considerations.
5. Recommended Test Procedures
Constituting One Cycle of Tests
In order to obtain the performance
data in addition to the water test, the first cycle
of tests should include the following steps.
a. Air Infiltration Test
b. Wind Load Tests at the
Maximum Positive and Negative Design Intensity.
c. Three cycles of story drift
at the maximum design story drift or L/100 where
L is the story height.
d. Water test in accordance with
Items 1 to 3 above.
The second cycle and beyond should
include the following steps.
a. Twenty cycles of story drift
at 50% of the maximum design story drift or
L/200 where L is the story height.
b. Water test in accordance with
Items 1 to 3 above.
6. Performance Rating Based on
Sustained Number of Cycles of Tests
The complete test procedures should
include the following steps.
Step 1 : Conduct Cycle1 test. If
no water leakage occurs, proceed to Step 2.
Step 2 : Conduct Cycle 2 test.
If no water leakage occurs, proceed to Step 3.
Step 3 : Repeat Step 2 and
counting the number of Cycles up to a maximum of
10 Cycles or until water leakage is observed.
The recommended performance
rating notation is illustrated by the following
example. A rating of A-C3 means Grade A test
sustaining 3 cycles of tests without water
leakage.
7. Standard Mock-up Size, Panel
and Support Arrangements
A performance rating system is for
comparing the performances among various curtain
wall systems. Therefore, in addition to the test
method, the test mock-up structure must also be
standardized. The following standard features on the
test mock-up are recommended.
a. Use three spaced apart
horizontal supporting beams for securing the
curtain wall mullions to simulate a two story
high structure. The center-to-center dimension
between two mullion securing points shall be 4
meters creating a two equal span structure at 4
meters each span. The total wall height shall be
8 meters plus the bottom and the top extensions
required by the curtain wall system to be
tested. The intermediate beam shall be the
movable beam for the story drift test.
b. Use the following sequential
panel arrangement on each bay between two
mullions starting from the bottom going
upwardly: one spandrel panel, one vision panel,
two spandrel panels, one vision panel, and one
spandrel panel at the top. The nominal height of
each vision panel shall be 1.6 m and the nominal
height of each spandrel panel shall be designed
to cover the entire wall height.
c. Use five mullions spaced at
1.5 m on centers to create four equal bays.
d. The typical top and bottom
details of the curtain wall system shall be used
on the mock-up.
e. If curable caulking is used
for any critical seal, the caulking must be
completely cured before commencing the test.
8. Additional Rating for
Inter-Floor Deflection
Due to the fact that the maximum
inter-floor deflection could occur and stay
stationarily during the entire duration of a
rainstorm, the water-tightness performance should be
evaluated at the deflected floor condition. This is
an in-service issue rather than a durability issue.
Therefore, the following separate conceptual rating
system is recommended.
a. Use a small mock-up with one
horizontal panel joint, one vertical panel
joint, and two mullion segments spliced
together. The bottom mullion segment is attached
to a horizontal beam which can move downwardly
to simulate the inter-floor deflection. The
arrangement should cause the horizontal panel
joint to enlarge.
b. Use the pressure chamber
method to conduct the water test with the
following two steps.
Step 1 : Water test with
zero beam deflection. It must pass this test
before going to Step 2 below.
Step 2 : Water test with a
beam deflection to be rated.
The recommended rating
notation after passing Step 2 test is
illustrated as follows. A rating of B-D10mm
means the system passes the water test with
a Grade B load at an inter-floor deflection
of 10mm.
Conclusions
Due to the rapidly increasing
concern about the liability caused by the water
leakage problem and the advances in curtain wall
technology in recent years, it is urgently needed in
the industry to have reliable and practical curtain
wall test method and procedures to develop a
performance rating system. To this end, the test
method and procedures must be revised to more
accurately simulate the effects of rainstorm on a
modern curtain wall system as well as to take into
account the measurement of performance durability.
The recommendations presented herein can only
represent a start of this effort in the conceptual
stage. A much bigger effort throughout the industry
is needed to finalize all details. Encouraging the
use of a better technology is the common goal of the
insurance industry and the curtain wall industry to
lessen the liability issue. This goal can only be
accomplished by a sensible performance rating
system. It is hoped that the building owners group,
the general contractors group, and the insurance
industry would form a task group to take the lead in
this effort since they will be benefited
significantly by reducing the liability exposure
caused by the water leakage problem.